The following sections of the Uniform Plumbing Code adopted by this chapter are hereby amended to read as follows:

A. Amend Section 104.3.3, Time Limitation of Application.

Applications for which no permit is issued within 365 days following the date of application shall expire by limitation, plans and other data submitted for review, thereafter, shall be returned to the applicant or destroyed by the Authority Having Jurisdiction. The Authority Having Jurisdiction shall be permitted to exceed the time for action by the applicant for a period not to exceed 365 days upon request by the applicant showing that circumstances beyond the control of the applicant have prevented the action from being taken. No application shall be extended more than once. In order to renew action on an application after expiration, the applicant shall resubmit plans and pay a new plan review fee.

B. Amend Section 104.4.3, Expiration.

A permit issued by the Authority Having Jurisdiction under the provisions of this code shall expire by limitation and become null and void where the work authorized by such permit is not commenced within 365 days from the date of such permit, or where the work authorized by such permit is suspended or abandoned at a time after the work is commenced for a period of 365 days. Before such work is recommenced, a permit shall first be obtained to do so, and the fee, therefore, shall be one-half the amount required for a new permit for such work, provided no changes have been made or will be made in the original construction documents for such work, and provided further that such suspension or abandonment has not exceeded 1 year.

C. Amend Section 104.4.4, Extensions.

A permittee holding an unexpired permit shall be permitted to apply for an extension of the time within which work shall be permitted to commence under that permit where the permittee is unable to commence work within the time required by this section. The Authority Having Jurisdiction shall be permitted to extend the time for action by the permittee for a period not exceeding 365 days upon written request by the permittee showing that circumstances beyond the control of the permittee have prevented the action from being taken. No permit shall be extended more than once unless authorized by the Building Official. In order to renew action on a permit after expiration, the permittee shall pay one half of permit fees for a new permit.

D. Amend Section 104.5, Fees.

A fee for each permit shall be paid as required, in accordance with the Redmond Zoning Code Section 21.76.030(E), as said chapter currently exists or is hereafter amended, modified or recodified.

E. Amend Section 104.5.3, Fee Refunds.

Section 108.6 Refunds of the administrative provisions of the International Building Code, Chapter 15.08 Redmond Municipal Code, shall apply.

F. Amend Section 106.3, Penalties.

Any person who violates a provision of this code or fails to comply with any of the requirements thereof or who erects, constructs, alters or repairs a building or structure plumbing system in violation of the approved construction documents or directive of the building official, or of a permit or certificate issued under the provisions of this code, shall be subject to the penalties provided for in RMC 1.01.110 and Chapter 1.14 Redmond Municipal Code, as said section currently exists or is hereafter amended, modified or recodified.

G. Amend Section 107.0, Board of Appeals.

Appeals of orders, decisions or determinations made by the Building Official related to the application or interpretation of this code shall be made pursuant to Redmond Zoning Code Section 21.76.060(I), Appeals of Type I and II Permits, as said section currently exists or is hereafter amended, modified or recodified.

(Ord. 3007 § 5, 2020; Ord. 2833 § 4 (part), 2016: Ord. 2729 § 7 (part), 2014: Ord. 2596 § 2 (part), 2011; Ord. 2346 § 5 (part), 2007: Ord. 2219 § 6 (part), 2004).